This project consisted of a CIP concrete wet well and two custom cast in place manhole structures which were all built around an active 96” diameter gravity feed sewer truck line running through the south end of Seattle. The three separate structures are all subterranean and were constructed within sheet pile shored excavations. The nature of working around an active sewer line required detailed sequencing and scheduling of the work to take place during low flow periods.
GC: JW Fowler Co.
Owner: King County, WA
Location: Seattle, WA
Contracted Amount: $378,828.36